The client required a temporary roof to install in the difficult site location of Beziers, with narrow streets and limited access for scaffolding. The temporary roof was positioned and installed, bay by bay, at ground level and lifted into place.
Date: | June 2015 |
Duration: | 12 months |
Customer: | Altrad Plettac Mefran |
Provision: | Supply |
System: | Altrix Roof |
Span: | 18m |
Length: | 25m |
Build Method: | Crane |