The client required a temporary roof to install in the difficult site location of Beziers, with narrow streets and limited access for scaffolding. The temporary roof was positioned and installed, bay by bay, at ground level and lifted into place.

Date: June 2015
Duration: 12 months
Customer: Altrad Plettac Mefran
Provision: Supply
System: Altrix Roof
Span: 18m
Length: 25m
Build Method: Crane