X

This project required a temporary public access bridge over an existing roadway. DESSA designed the overall scheme to integrate the Asterix HD beams (complete with aluminium lacing and bracing elements) with a Plettac system scaffold. The Asterix HD beams were overlaid with timber battens and clad in plywood to support the public.

Facts & Figures

Date: October 2018
Duration: 12 months
Customer: TD-S
Provision: Design and Supply
System: Asterix HD
Span: 18m